City wastes money on project designs, councillor says

Advertisement

Advertise with us

The City of Winnipeg could impose strict criteria for when a project warrants a detailed design, following concerns it has spent millions exploring projects that don’t get built.

Read this article for free:

or

Already have an account? Log in here »

To continue reading, please subscribe:

Monthly Digital Subscription

$19 $0 for the first 4 weeks*

  • Enjoy unlimited reading on winnipegfreepress.com
  • Read the E-Edition, our digital replica newspaper
  • Access News Break, our award-winning app
  • Play interactive puzzles
Continue

*No charge for 4 weeks then billed as $19 every four weeks (new subscribers and qualified returning subscribers only). Cancel anytime.

Hey there, time traveller!
This article was published 23/05/2022 (849 days ago), so information in it may no longer be current.

The City of Winnipeg could impose strict criteria for when a project warrants a detailed design, following concerns it has spent millions exploring projects that don’t get built.

“It’s city practice to do… functional designs, which are detailed designs of major infrastructure projects. And those things are done in advance of having funding for (the project). As a result, we have a number of them on the books that are designed but they’re not funded,” said Coun. Matt Allard.

“We have several projects that have a lot of merit and several projects that should be built, if we had the money. However, if you add them up, it’s clear as day that we don’t have the funding.”

MIKAELA MACKENZIE / WINNIPEG FREE PRESS FILES
Coun. Matt Allard: “I would like us to not spend money until we know that there’s a political desire to pursue a project”
MIKAELA MACKENZIE / WINNIPEG FREE PRESS FILES Coun. Matt Allard: “I would like us to not spend money until we know that there’s a political desire to pursue a project”

Allard, who is council’s public works chairman, is calling for city staff to study the idea of putting conditions in place before money is spent on a functional design. He believes each project should have a class five (quite preliminary) cost estimate and a minimum of 40 per cent of its total price included in Winnipeg’s five-year capital budget forecast to qualify for that design.

Allard’s motion calls for future functional designs to include a 30-year forecast of operating and maintenance costs for each project, as well as an assessment of how it will affect the city’s tax base, including the impact of properties acquired to make room for it.

If public works agrees, the report would also explore options to have city staff to manage functional designs in-house, without turning to consultants.

“I’m trying to get more information on the table and I would like us to not spend money until we know that there’s a political desire to pursue a project,” said Allard.

He estimates the city has spent several million dollars in recent years on consultant studies for major projects that remain unfunded, indefinitely postponed or cancelled. That includes $1.25 million to design a widening and grade separation for Marion Street. That project was abandoned in 2016, largely because its $566-million price was deemed too expensive, said Allard.

“I think (these proposed changes are) tightening up our processes so that we don’t spend money before we need to do so,” Allard told his colleagues on the Riel community committee just before they approved the motion on Tuesday. “Why not save millions of dollars, do the political work and then actually build something?”

The councillor told the Free Press additional design work on the William R. Clement Parkway, Arlington Bridge, Kenaston Boulevard and Chief Peguis Trail cost a combined $7.9 million, while the related projects have yet to be pursued.

In an email, city spokesman Kalen Qually said the public service will review Allard’s specific motion.

However, Qually said functional and preliminary design studies are needed to develop cost estimates that are “suitable for budgeting purposes.”

He said such work often can’t be completed by city staff.

“Many functional designs require specialized engineering expertise that may not exist within the public service. In addition, internal staff resources are not available to undertake the investigations necessary to develop many of these projects,” said Qually.

The statement cautioned against deeming the functional design spending to be a waste.

“Preliminary work may be completed well ahead of construction so it’s difficult to say certain projects won’t be completed,” he said.

The public works committee will consider Allard’s motion on June 9.

Joyanne.pursaga@freepress.mb.ca

Twitter: @joyanne_pursaga

Joyanne Pursaga

Joyanne Pursaga
Reporter

Born and raised in Winnipeg, Joyanne loves to tell the stories of this city, especially when politics is involved. Joyanne became the city hall reporter for the Winnipeg Free Press in early 2020.

Our newsroom depends on a growing audience of readers to power our journalism. If you are not a paid reader, please consider becoming a subscriber.

Our newsroom depends on its audience of readers to power our journalism. Thank you for your support.

Report Error Submit a Tip

Local

LOAD MORE